Two Home Lifts Delivered from Planning to Handover in North Willoughby

Home lift installation process at a North Willoughby residence

Two Home Lifts Delivered from Planning to Handover in North Willoughby

Home lift installation process at a North Willoughby residence

Executive Summary

Electric Home Lift Installation in North Willoughby – Two Lifts, One Duplex, Delivered in Stages

A residential project in North Willoughby required two electric home lifts to serve two separate units in the duplex house.
The project involved extensive coordination between the client, lift team and building works, including architectural drawing reviews, site measurements, lift design, finishes selection, manufacturing, delivery and installation.
Following several rounds of design review and site coordination, the lift specifications and finishes were confirmed, and manufacturing commenced. The two lifts were subsequently delivered to site and installed in stages as the building works progressed.
In 2025, both lifts had been fully installed, tested, defects resolved and formally handed over to the client. The lifts were passed into service, with the relevant completion and handover documentation subsequently provided to the client.

The Client & The Challenge

The Challenge – Designing Two Home Lifts for a New House on Sydney’s Lower North Shore

The client was developing a duplex residential property at North Willoughby and required two home lifts as part of the project.
At the early planning stage, several key details were still being finalised, including shaft dimensions, headroom, travel distance, pit depth, floor levels and door configuration. The architectural drawings were also subject to approval, which meant the lift requirements needed to be reviewed and updated as the building plans developed.
As the project progressed, accurate site measurements and coordination with the building works became increasingly important. The lift drawings, finishes, accessories and specifications all needed to be confirmed before manufacturing could proceed.
The client also wanted to understand how the proposed lift would look in the completed homes. Finished lift photographs were provided as a visual reference, alongside continued discussions around the lift design and installation requirements.

The Solution

Our Approach to Residential Lift Installation in NSW – Site Measure, Drawings and Finishes

The project began with a review of the client’s architectural information and clarification of the key lift requirements.
Following further design development and site discussions, a site inspection was carried out in 2024 to take measurements and document the existing conditions. The lift drawings and site inspection information were then updated for the client’s review.
During July, the client confirmed the shaft dimensions, floor-to-floor requirements and selected finishes. Multiple drawing updates were exchanged to ensure the specifications were clearly established before production.
The final finishes schedule was issued for review and signature in July 2024. The approved schedule specified wood-grain steel plates, a mirror-finish stainless steel feature panel, aluminium alloy and white acrylic ceiling finishes, 10-inch touch-screen car operating panels, and black titanium sandblasted stainless-steel doors and frames.
Once the drawings and finishes were confirmed, the project proceeded to manufacturing.
Delivery was coordinated after further site preparation and inspection. The delivery documentation confirmed that the lift equipment was delivered to the North Willoughby site in multiple cases.
Installation then progressed in stages as the building works advanced. Then the West lift was approaching completion while installation of the East lift was underway.

Results Achieved

Results – Two Electric Home Lifts Tested, Commissioned and Handed Over

By 2025, both home lifts had been completed and formally handed over to the client.
The completed works included:
• Supply and installation of two electric home lifts
• Lift programming
• Testing and commissioning
• Resolution of outstanding defects
• Final handover to the client
• Completion documentation and ongoing maintenance information
The project records confirm that both lifts were completed, tested and passed into service in 2025, with no visible damage recorded at handover.
Following completion, the client was also provided with the relevant completion documentation, warranty information and lift door cleaning guidance to support ongoing care and maintenance.

Future Recommendations & Key Takeaways

Key Takeaways for Home Lift Installation in Sydney During Construction

This project demonstrates the importance of early planning and continuous coordination when installing home lifts as part of a residential construction project.
From the initial architectural review through to final handover, the lift requirements evolved alongside the building project. Regular drawing reviews, site inspections and communication with the client helped ensure that dimensions, finishes and installation requirements were confirmed before each major stage.
With both lifts successfully installed, tested and handed over, the project was brought through from initial planning to completed operation.